Hawai‘i Department of Transportation announces the following 10 scheduled lane closures and road work projects on Kaua‘i state roadways during the week of Jan. 3-9.
* * * * * * * * *

HIGHWAY 50
KĪPŪ
- SINGLE LANE CLOSURE possible in either direction, between mile posts 2.9 and 8.4 in the vicinity of Kīpū Road and Puneʻe Road, from 9 p.m. to 5 a.m. Jan. 4-9 for rumble strip and striping work. Traffic will be routed through the open lane.
HIGHWAY 51
NĀWILIWILI
- SINGLE LANE CLOSURE possible in either direction, near mile posts 0 and 0.8 in the vicinity of Waʻa-pā Road and Kapule Highway, from 8:30 a.m. to 3:30 p.m. Jan. 5-9 for sidewalk, curbing, median and ramp work. Traffic will be routed through the open lane.
HIGHWAYS 56/560
ARTICLE CONTINUES BELOW AD
ARTICLE CONTINUES BELOW AD
LĪHU‘E
- SINGLE LANE CLOSURE in the southbound direction, between mile posts 0.1 and 0.3 in the vicinity of Hardy Street and Poinciana Street, from 9 p.m. to 5 a.m. Jan. 4-9 for waterline replacement.
WAILUĀ
- FULL CLOSURE in the southbound direction, between mile posts 5.7 and 5.9 in the vicinity of Wailuā State Park Road and Kuamoʻo Road, from 9 p.m. to 5 a.m. Jan. 5-9 for concrete work on the Wailua Mauka Bridge. Traffic will be routed to the Wailua Plantation Bridge.
KAPAʻA
- SINGLE LANE CLOSURE possible in either direction, between mile posts 8 and 9.5 in the vicinity of ʻAkia Road, from 8:30 a.m. to 3:30 p.m. Jan. 5-9 for concrete work. Alternating traffic will be routed through the open lane.
ADVERTISEMENT
KALIHIWAI TO PRINCEVILLE
- LANE SHIFT possible in either direction, between mile posts 24.4 and 28.1 in the vicinity of Kahiliholo Road to Emmalani Drive, from 8 p.m. to 5 a.m. Jan. 5-9 for striping.
HANALEI
- SINGLE LANE CLOSURE possible in either direction, between mile posts 1.2 and 2.4 in the vicinity of ʻŌhiki Road and Papio Place, from 8:30 a.m. to 3:30 p.m. Jan. 5-9 for guardrail work. Alternating traffic will be routed through the open lane.
WAIKOKO
- SINGLE LANE CLOSURE possible in either direction, between mile posts 4.6 and 4.8 in the vicinity of Waikoko Bridge and Lumahaʻi Beach, from 8:30 a.m. to 4:30 p.m. Jan. 5-9 for soil nail drilling, grouting and concrete work. Alternating traffic will be routed through the open lane.
HIGHWAY 58
ARTICLE CONTINUES BELOW AD
NĀWILIWILI
- SINGLE LANE CLOSURE possible in either direction near mile post 0, in the vicinity of Waʻa-pā Road, from 8:30 a.m. to 12:30 p.m. Jan. 5 for crosswalk restriping.
HIGHWAY 550
KŌKE‘E
- FULL CLOSURE between mile posts 1.1 and 6.7, in the vicinity of Panini Place and Kōkeʻe Road, from 7 a.m. to 5:30 p.m. Jan. 5-9 for pavement reconstruction and resurfacing. Traffic will be detoured to Kōkeʻe Road.
* * * * * * * * *
Lane closure schedules can change at any time without further notice. All projects are weather permitting.
A map of lane closures can be found online.